Construction Work Update, James Brindley Way, Sandyford

Caddick Construction have supplied Sandyford & Goldenhill Residents Association with a progress update on the new phase 2 development on James Brindley Way, Sandyford.

Unit 1 steel frame complete and roof and wall cladding commenced.

Unit 2/4 steel frame complete and prepping for ground floor office area and 1st floor concrete slab pours.

Unit 3 steel frame complete and commenced roof cladding

Unit 5 steel frame complete and commenced roof cladding

Ongoing groundworks including drainage installation. Unit 2 car park and access road into site has now been tarmaced to keep the access and egress into site clean which helps keeping James Brindley Way road clean.

Also, we have the 1st floor concrete slabs to unit 2/4 which is the unit to the rear of the site being poured next Wednesday (04/05/22) so there will be a nightshift which will once again have power floating and lighting through the night.

Leave a Reply

You can use these HTML tags

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

  

  

  


The reCAPTCHA verification period has expired. Please reload the page.